We would like to take the opportunity to introduce ourselves as the point of contact for Kier Regional Building London & South East who have been appointed to undertake the construction of Marylebone Square.
Our project
The works at Marylebone consist of constructing a collection of both high-end and affordable apartments over 5 storey, carefully chosen boutiques and restaurants, and a versatile community hall.
Progress update - October:
Works will commence along St Vincent Street on 26.10.2020
Main works will be installation of Kingposts walls around the perimeter of site to enable the basement to be constructed.
Main construction works due to start in November 2020
There will be various hoarding changes occurring during the initial period before a permanent hoarding is installed. Deliveries will be met at the southside of Aybrook Street prior to entering site.
The next community liaison group meeting will take place next Wednesday 21st October 17:30 to 18:30 via zoom. Please email marylebonesquare@fourcommunications.com to confirm attendance.