The initial programme is as follows.
31st October 2018 – Car park closes to the public
1st to 30th November 2018 – Disconnections of power & water utilities on site, and removal of street furniture
1st December 2018 – Commencement of Enabling Works: Installation of site cabins and temporary perimeter hoarding (heras fence), removal of car park tarmac, barriers and pavement vaults
To find out more visit http://www.moxonstreetcarpark.com